CONSTRUCTION UPDATE : JANUARY 2019
15.01/2019

Bluphere Pattaya Managed By BW Premier Collection

Update: 15 January 2019

20% Overall construction work completed.

The environmental impact assessment has been approved.


Wyndham Atlas Wongamat Pattaya

Update: 15 January 2019

4% Overall construction work completed.

The environmental impact assessment has been approved.

 


 

X2 Pattaya Oceanphere 

Update: 15 January 2019

90% Overall construction work completed. 

A construction permit has already been issued.

 


Best Western Premier Bayphere Pattaya 

Update: 15 January 2019

90% Overall construction work completed.

The environmental impact assessment has been approved.